Adding Resource to task in Project manager

Previous Topic Next Topic
 
classic Classic list List threaded Threaded
2 messages Options
Reply | Threaded
Open this post in threaded view
|

Adding Resource to task in Project manager

gcameo
I am trying to add resources to a task as described in this document:

http://docs.ofbiz.org/display/OFBENDUSER/Project+Manager+Application+Roles

but I keep getting this error





 
    The Following Errors Occurred:
        In set-nonpk-fields a value was not found with the specified valueAcsr: assignment, not setting fields
How do I fix this.
Thanks
Regards

 





Reply | Threaded
Open this post in threaded view
|

Re: Adding Resource to task in Project manager

gcameo
I have just tried this on the demo server here
https://demo904.ofbiz.org/projectmgr/control/createTaskPartyAssign

and it came back with the same error:

In set-nonpk-fields a value was not found with the specified valueAcsr: assignment, not setting fields

Any ideas how to fix this?

--- On Wed, 17/6/09, farouk alhassan <[hidden email]> wrote:

From: farouk alhassan <[hidden email]>
Subject: Adding Resource to task in Project manager
To: [hidden email]
Date: Wednesday, 17 June, 2009, 4:19 AM

I am trying to add resources to a task as described in this document:

http://docs.ofbiz.org/display/OFBENDUSER/Project+Manager+Application+Roles

but I keep getting this error





 
    The Following Errors Occurred:
        In set-nonpk-fields a value was not found with the specified valueAcsr: assignment, not setting fields
How do I fix this.
Thanks
Regards