Jacopo Cappellato commented on OFBIZ-427:
-----------------------------------------
Some Ideas (taken from a mail I've recently sent to the user list):
let's say that your forecast is to sell 10000 t-shirt of type "A" in the next 2 months; the t-shirt "A" are virtual product that are available in two sizes, S and L.
You would like to simulate (materials and resources needed) the manufacturing process to create 10000 t-shirt of type "A", regardless of their sizes.
I'd recommend to implement something different:
1) introduce the concept of a "family of products"; this could be a special type of Product that is only used as a planning tool; in the example above, you could create a new product of type "family of products" to represent your type "A" t-shirts
2) create a bom for your family of products where each component is a variant product; for example: family "A" has two components, the variant product "t-shirt A size S" and "t-shirt A size L"; the bom coefficient is used here to forecast the number of sizes that will be sold (for example, 0.4 for S and 0.6 for L)
3) then you'll create one production run for the family "A" of 10000 units with start date in the future; the production run will never be executed (i.e. its components, the variant products, will not be taken from warehouse)
4) by running the MRP you'll get a simulation of the materials needed (to manufacture 4000 t-shirt of size S and 6000 t-shirt of size L) and it will generate the *requirements* for them (that once approved will become new production runs for real variant products).
> MRP - implement sales forecast analysis
> ---------------------------------------
>
> Key: OFBIZ-427
> URL:
http://jira.undersunconsulting.com/browse/OFBIZ-427> Project: [OFBiz] Open For Business
> Type: New Feature
> Components: manufacturing
> Versions: SVN
> Reporter: Jacopo Cappellato
> Assignee: Jacopo Cappellato
> Priority: Minor
>
> Original Estimate: 2 weeks
> Remaining: 2 weeks
>
> MRP - implement sales forecast analysis
> At the beginning of the simulation process, the MRP algorithm collects information about real purchase orders, sales orders, production runs and stock levels.
> We should add to these the sales forecasts; this issue involves:
> * ui and services to manage (create/edit/delete) sales forcasts
> * entities to store them
> * entities to store families of products (ProductCategories?)
> * mods to the MRP process
--
This message is automatically generated by JIRA.
-
If you think it was sent incorrectly contact one of the administrators:
http://jira.undersunconsulting.com/secure/Administrators.jspa-
For more information on JIRA, see:
http://www.atlassian.com/software/jira