Hi James,
You can link the task during BoM setup with Routing Task field from UI and
this field store in product_assoc.routing_work_effort_id field and when you
create the job then all the product automatically link with the respective
routing task.

Kind Regards,
Yashwant Dhakad
Sr. Technical Consultant

*HotWax Systems*
*Enterprise open source experts*
cell: +91-9098240513
office: 0731-409-3684
http://www.hotwaxsystems.com


On Thu, Feb 4, 2021 at 9:39 AM <[hidden email]> wrote:

> All we are setting up a BOM, Routing and Routing Tasks that operates as
> follows
>
> My Routing will consist of the following Routing Tasks
>
> Task 1
> Task 2
> Task 3
>
> My BOM is made up of 5 Products
> Product 1 - Associated with Task 1
> Product 2-Associated with Task 1
> Product 3-Associated with Task 2
> Product 4-Associated with Task 2
> Product 5-Associated with Task 2
>
> When running the production run I want product picked based on the tasks
> they are associated with.  Is this possible?
>
> We are having issues where ALL of the BOM is not showing up on the
> Production run
>