Requirements is based on a handful of factors including Min. Stock,
Sales Orders, Sales Forecast, Scheduled Production Run <for Product
Requirements>; You might want to check these
- Regards
Sakthi
On 5/17/12, Venkat Mangudi <
[hidden email]> wrote:
> MRP created a requirement for a product that already has a previously
> closed requirement (closed because the requirement was used to place
> order). It did not do this for all the products, but only a few. I wonder
> what could have caused this inconsistency. Any thoughts?
>
> --
> Regards,
> Venkat
>
--