https://issues.apache.org/jira/browse/OFBIZ-7128?page=com.atlassian.jira.plugin.system.issuetabpanels:all-tabpanel ]
Swapnil Shah closed OFBIZ-7128.
-------------------------------
Thanks [~rahul.bhooteshwar] for the fixes. I have tested it and found it working as per expected behavior outlines in description.
Here are test results:
# Run MRP and generate multiple requirements,
# Approve the requirement and use the same during purchase ordering by selecting eligible supplier
# Submit the order and found the Requirement>>Order tab reflecting the correct order id linking with used requirement (*PASS*)
> Purchase Order created out of Approved Product Requirement are not getting linked/shown over Requirement>>Order screen
> ----------------------------------------------------------------------------------------------------------------------
>
> Key: OFBIZ-7128
> URL:
https://issues.apache.org/jira/browse/OFBIZ-7128> Project: OFBiz
> Issue Type: Bug
> Components: order
> Reporter: Swapnil Shah
> Assignee: Swapnil Shah
> Fix For: 14.12.01, 15.12.01
>
> Attachments: OFBIZ-7128, ReqtoPO_1.png, ReqtoPO_2.png, ReqtoPO_3.png, ReqtoPO_4.png, ReqtoPO_5.png
>
>
> Once any product requirement created out of MRP run or independently get approved, becomes eligible for being used/converted to purchase order. But once PO is created out of such requirements, it doesn't get linked/listed on Requirement >> Order screen
> Please refer to attached screenshots for chain of events and reference
--
This message was sent by Atlassian JIRA