[jira] [Created] (OFBIZ-5604) Add nextTask field to production run declaration form dependent on time entry additions

Previous Topic Next Topic
 
classic Classic list List threaded Threaded
1 message Options
Reply | Threaded
Open this post in threaded view
|

[jira] [Created] (OFBIZ-5604) Add nextTask field to production run declaration form dependent on time entry additions

Nicolas Malin (Jira)
Christian Carlow created OFBIZ-5604:
---------------------------------------

             Summary: Add nextTask field to production run declaration form dependent on time entry additions
                 Key: OFBIZ-5604
                 URL: https://issues.apache.org/jira/browse/OFBIZ-5604
             Project: OFBiz
          Issue Type: Improvement
    Affects Versions: SVN trunk
            Reporter: Christian Carlow


I'm faced with the challenge of recreating a company's WIP report using OFBiz manufacturing data.  The purpose of the WIP report in OFBiz terms is to indicate how many pieces have moved to fixed assets by a previous task declaration based on the time entry functionality added in OFBIZ-5532.  I propose adding an additional nextTaskId field dependent on the added time entry functionality to generate an inventory list for production run task fixed assets.  

For example:
Given a production run with 3 tasks all with differing fixed assets and able to be performed in any order, if a user creates a timeEntry declaration for task1 and sets the nextTaskId to task3 then I could generate a WIP report indicating that the quantityProduced exists at the fixedAsset of task3.



--
This message was sent by Atlassian JIRA