Swapnil Shah created OFBIZ-7173:
-----------------------------------
Summary: The Product Added from 'Actual Material' screen could be consumed for producing end product during routing task execution
Key: OFBIZ-7173
URL:
https://issues.apache.org/jira/browse/OFBIZ-7173 Project: OFBiz
Issue Type: New Feature
Reporter: Swapnil Shah
Assignee: Divesh Dutta
Currently any new product added against given routing task via Actual Material screen just reflects the inventory statistics it.
We could try to add the feature of having the added products actually be added in conjunction with Actual projected Material requirement based on original BoM associated with the routing.
# This could be done by creating fresh WorkEffortGoodStandard (WEGS) with such added products against specified routing.
# We can begin with simple constraint of allowing new material against the only those routing task that has not completed/cancelled yet within a production run
# Start showing such newly added material requirement in conjunction with original requirement (based on BoM) under all relevant sections over Production Declaration Screen
Please refer to attached screenshot for reference
--
This message was sent by Atlassian JIRA