[jira] [Created] (OFBIZ-7468) [OFBIZ-7173] Actions on adding new material to the task which is in completed/cancel status.

Previous Topic Next Topic
 
classic Classic list List threaded Threaded
1 message Options
Reply | Threaded
Open this post in threaded view
|

[jira] [Created] (OFBIZ-7468) [OFBIZ-7173] Actions on adding new material to the task which is in completed/cancel status.

Nicolas Malin (Jira)
Anuj Jain created OFBIZ-7468:
--------------------------------

             Summary: [OFBIZ-7173] Actions on adding new material to the task  which is in completed/cancel status.
                 Key: OFBIZ-7468
                 URL: https://issues.apache.org/jira/browse/OFBIZ-7468
             Project: OFBiz
          Issue Type: Sub-task
          Components: manufacturing
    Affects Versions: Trunk
            Reporter: Anuj Jain


Define actions on adding new material to the task which is in completed/cancel status.

Actions suggested by Swapnil :-

# We can begin with simple constraint of allowing new material against the only those routing task that has not cancelled yet within a production run
# Any completed taks should have WEGS created in COMPLETED status and WEIA created as well by issuing the added item's qty.




--
This message was sent by Atlassian JIRA
(v6.3.4#6332)