Anuj Jain created OFBIZ-7468:
--------------------------------
Summary: [OFBIZ-7173] Actions on adding new material to the task which is in completed/cancel status.
Key: OFBIZ-7468
URL:
https://issues.apache.org/jira/browse/OFBIZ-7468 Project: OFBiz
Issue Type: Sub-task
Components: manufacturing
Affects Versions: Trunk
Reporter: Anuj Jain
Define actions on adding new material to the task which is in completed/cancel status.
Actions suggested by Swapnil :-
# We can begin with simple constraint of allowing new material against the only those routing task that has not cancelled yet within a production run
# Any completed taks should have WEGS created in COMPLETED status and WEIA created as well by issuing the added item's qty.
--