[jira] [Updated] (OFBIZ-7110) The Actual Material Cost is not accounting for cost of returned items against the issued items for production run tasks

Nicolas Malin (Jira)

     [ https://issues.apache.org/jira/browse/OFBIZ-7110?page=com.atlassian.jira.plugin.system.issuetabpanels:all-tabpanel ]

Divesh Dutta updated OFBIZ-7110:
--------------------------------
    Assignee: Anuj Jain  (was: Divesh Dutta)

> The Actual Material Cost is not accounting for cost of returned items against the issued items for production run tasks
> -----------------------------------------------------------------------------------------------------------------------
>
>                 Key: OFBIZ-7110
>                 URL: https://issues.apache.org/jira/browse/OFBIZ-7110
>             Project: OFBiz
>          Issue Type: New Feature
>          Components: manufacturing
>    Affects Versions: Release Branch 14.12, 14.12.01, Release Branch 15.12, 15.12.01
>            Reporter: Swapnil Shah
>            Assignee: Anuj Jain
>         Attachments: MatCost_1.png, Matcost_2.png, OFBIZ-7110.patch
>
>
> As of now the 'Actual Material Cost' over Actual Cost tab for any production run just shown as weighted sums up of the issued inventory's cost.
> We could allow it to account for returned items as well by deducting weighted sum of returned inventory's cost from the weighted sum of issued inventory's cost.
> Please refer to attached screenshot for more details



--