Pierre Smits updated OFBIZ-8243:
--------------------------------
Attachment: Screen Shot 2016-09-14 at 08.33.10.png
In attached screenshot you'll see 5 tasks, and when looking at
* task 4 (ferment 3 days) starts on 2016-09-13 15:00:00.000 and ends at 2016-09-26 15:00:00.000, gives a throughput time of 13 days, while the actual throughput time was 3 days.
* task 5 (lager 28 days) starts on 2016-09-26 15:00:00.000 and ends at 2017-01-20 14:00:00.000, gives a throughput time of 116 days, while the actual throughput time was 28 days.
> End date calculation of workefforts is wrong
> --------------------------------------------
>
> Key: OFBIZ-8243
> URL:
https://issues.apache.org/jira/browse/OFBIZ-8243> Project: OFBiz
> Issue Type: Bug
> Components: manufacturing, workeffort
> Affects Versions: Release Branch 14.12, Trunk, Release Branch 15.12
> Reporter: Pierre Smits
> Assignee: Pierre Smits
> Labels: productionrun, routing
> Attachments: Screen Shot 2016-09-14 at 08.33.10.png
>
>
> When a new production run is generated based on a production schema with tasks, the process takes the tasks of the schema (in the designated order) and calculate the start and end date for each task (based on the provided start date of the production run.
> This process doesn't work properly as tasks with a total throughput time (setup + run time) more than 1 day leads to wrong results.
--