Re: Question on Rouning tasks
Posted by
jonwimp on
Jan 18, 2007; 11:41am
URL: http://ofbiz.116.s1.nabble.com/Question-on-Rouning-tasks-tp143884p143885.html
Mike,
Once you start a routing task (when inside the Production Run screen), you can "Declare" certain
numbers for the routing task. I believe you can set the completion time there. Let me know what
you found? Thanks.
Jonathon
Mike Wong wrote:
> Hi All,
>
> One quick question.
>
> With the current version of OfBiz is it possible to create a "Rounting Task"
> which can simulate a job that can be done by multiple workers?
>
> All I can do now is a Task with an estimate usage time which will be
> multiply with the quantity to calculate the estimate job end time. I can't
> configure the task to if I can assign 2 workers to that task and the
> estimate end time should be cut to half.
>
> Thanks
> Mike
>
>
>