> Assigning a resource to a task is not reflected in the resource's tasks view.
> -----------------------------------------------------------------------------
>
> Key: OFBIZ-3638
> URL:
https://issues.apache.org/jira/browse/OFBIZ-3638> Project: OFBiz
> Issue Type: Bug
> Components: specialpurpose/projectmgr
> Affects Versions: SVN trunk
> Environment: Windows 7
> Reporter: Peter Radkov
> Assignee: Erwan de FERRIERES
> Attachments: OFBIZ-3638-AssigningResourceIsNotReflected.patch
>
>
> Steps to reproduce the bug:
> 1) Create a Project, a Phase and a Task (say "Observe the Bug").
> 2) Select the "Observe the Bug" task, go to its [Resources] sub-tab and assign a resource (Say "Tester") to it.
> 3) Now go to the resource "Tester" that you just assigned (from the Project's application main menu select [Resoruces] and then select "Tester" from the list).
> 4) Click on the "Tester"'s [Tasks] sub-tab and observe that the task "Observe the Bug" is NOT listed.