http://ofbiz.116.s1.nabble.com/jira-Reopened-OFBIZ-7468-Define-constraints-while-adding-new-material-to-the-task-which-is-in-comple-tp4700510.html
> Define constraints while adding new material to the task which is in completed/cancel status.
> ---------------------------------------------------------------------------------------------
>
> Key: OFBIZ-7468
> URL:
https://issues.apache.org/jira/browse/OFBIZ-7468> Project: OFBiz
> Issue Type: Improvement
> Components: manufacturing
> Affects Versions: Trunk
> Reporter: Anuj Jain
> Assignee: Anuj Jain
> Attachments: OFBIZ-7468.patch, OFBIZ_7468_1.png, OFBIZ_7468_2.png, OFBIZ_7468_3.png
>
>
> Define actions on adding new material to the task which is in completed/cancel status.
> Actions suggested by Swapnil :-
> # We can begin with simple constraint of allowing new material against the only those routing task that has not cancelled yet within a production run
> # Any completed taks for uncomplete Production Run should have WEGS created in COMPLETED status and WEIA created as well by issuing the added item's qty.
> # If production is already completed (aka all its routing task also completed/cancelled) then don't allow new material to be added from Actual Material screen