Hi people
The problem: In opentaps-0.94 Manufacturing->Approve requirements gives me a blank list even though I have done a Run MRP. The Inventory event planned gives incomplete results as well. I am not sure if what I am seeing is a bug, configuration issue or just a misunderstanding on my part. Any suggestions would be gratefully received. I posted this message to the opentaps users list and Jacques Le Roux suggested that this message was more suited to this list. The steps I have taken to repeatably produce this problem: Add items with lowest level items as raw materials. 3rd level items are WIPs and 2nd level items are sub-assemblies and the finished product (V164) is a finished product. Created a multi-level BOM following the instructions in: sequoiaerp-0.8-manufacturing-1-create-bill-of-materials-avi.zip and opentaps-0.9-manuals-v5.zip Screenshots of the exploded BOM created can be found at: http://209.59.210.118/MRPsnapshots/explodedbom1.png and http://209.59.210.118/MRPsnapshots/explodedbom2.png Place an order for a series of finished products, V164 (See screenshot at http://209.59.210.118/MRPsnapshots/order.png <http://209.59.210.118/MRPsnapshots/order.png%29> ) Manufacturing->Run MRPusing called TEST (screenshot at http://209.59.210.118/MRPsnapshots/runmrp.png <http://209.59.210.118/MRPsnapshots/runmrp.png%29> ) I ran the inventory event planned option, which gave strange and incomplete results ( http://209.59.210.118/MRPsnapshots/inventory_event_planned.png ) listing only the finished product, V164, and the 1st level subassembly, COREV18A. No raw materials of WIPs are displayed. Going to approve requirements ( http://209.59.210.118/MRPsnapshots/approve_requirements.png ) gave me an empty result, even if I searched a product (e.g. any of the COREV18A, V164, etc.) or MRP related queries. What I have done to try to correct the problem so far: Try to search for a component in the approve requirements screen that I know is in the BOM. No change. Still a blank result as shown in the screenshot http://209.59.210.118/MRPsnapshots/approve_requirements.png. Try to change the various components in the BOM to different types. Currently all COREV18A% items are WIPs, other than COREV18A itself, which is a subassembly. V164 is a finished product and all the 717% items are raw materials. Changing the WIPs to raw materials, subassemblies or finished products does nothing to help. My system: Linux Fedora Core 6 running with 1.5GB RAM and several GBs of free hard drive space I am running opentaps 0.94 with Mysql 5.0 using the set up instructions for opentaps-mysql integration at opentaps-0.9-configuring-for-mysql-screenshots.zip Many thanks for any replies and suggestions Regards Mark |
Mark,
I have two quick suggestions: 1) you should create the ProductFacility records for your products and components (this is done in Catalog->Product->Facility screen) 2) you should really try to use the OFBiz trunk, since recently the MRP has been enhanced Jacopo Mark wrote: > Hi people > > The problem: > In opentaps-0.94 Manufacturing->Approve requirements gives me a blank > list even though I have done a Run MRP. > The Inventory event planned gives incomplete results as well. > > I am not sure if what I am seeing is a bug, configuration issue or just > a misunderstanding on my part. Any suggestions would be gratefully > received. I posted this message to the opentaps users list and Jacques > Le Roux suggested that this message was more suited to this list. > > The steps I have taken to repeatably produce this problem: > Add items with lowest level items as raw materials. 3rd level items are > WIPs and 2nd level items are sub-assemblies and the finished product > (V164) is a finished product. > Created a multi-level BOM following the instructions in: > sequoiaerp-0.8-manufacturing-1-create-bill-of-materials-avi.zip and > opentaps-0.9-manuals-v5.zip > Screenshots of the exploded BOM created can be found at: > http://209.59.210.118/MRPsnapshots/explodedbom1.png and > http://209.59.210.118/MRPsnapshots/explodedbom2.png > Place an order for a series of finished products, V164 (See screenshot > at http://209.59.210.118/MRPsnapshots/order.png > <http://209.59.210.118/MRPsnapshots/order.png%29> ) > Manufacturing->Run MRPusing called TEST (screenshot at > http://209.59.210.118/MRPsnapshots/runmrp.png > <http://209.59.210.118/MRPsnapshots/runmrp.png%29> ) > I ran the inventory event planned option, which gave strange and > incomplete results ( > http://209.59.210.118/MRPsnapshots/inventory_event_planned.png ) listing > only the finished product, V164, and the 1st level subassembly, > COREV18A. No raw materials of WIPs are displayed. > Going to approve requirements ( > http://209.59.210.118/MRPsnapshots/approve_requirements.png ) gave me an > empty result, even if I searched a product (e.g. any of the COREV18A, > V164, etc.) or MRP related queries. > > What I have done to try to correct the problem so far: > Try to search for a component in the approve requirements screen that I > know is in the BOM. No change. Still a blank result as shown in the > screenshot http://209.59.210.118/MRPsnapshots/approve_requirements.png. > Try to change the various components in the BOM to different types. > Currently all COREV18A% items are WIPs, other than COREV18A itself, > which is a subassembly. V164 is a finished product and all the 717% > items are raw materials. Changing the WIPs to raw materials, > subassemblies or finished products does nothing to help. > > My system: > Linux Fedora Core 6 running with 1.5GB RAM and several GBs of free hard > drive space > I am running opentaps 0.94 with Mysql 5.0 using the set up instructions > for opentaps-mysql integration at > opentaps-0.9-configuring-for-mysql-screenshots.zip > > Many thanks for any replies and suggestions > Regards > Mark > |
Free forum by Nabble | Edit this page |