[jira] [Created] (OFBIZ-4396) Project Manager Gantt chart does not display correctly using any of the visual themes

Previous Topic Next Topic
 
classic Classic list List threaded Threaded
38 messages Options
12
Reply | Threaded
Open this post in threaded view
|

[jira] [Commented] (OFBIZ-4396) Project Manager Gantt chart does not display correctly using any of the visual themes

Nicolas Malin (Jira)

    [ https://issues.apache.org/jira/browse/OFBIZ-4396?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=13119431#comment-13119431 ]

BJ Freeman commented on OFBIZ-4396:
-----------------------------------

The Link I gave shows a css just for gnatt chart.
So I would look if this css is loaded after the Themes or before.
Then look to see if any css in themes has any thing related tot he gnatt chart.
Due to my time, I don't have time to do this.
               

> Project Manager Gantt chart does not display correctly using any of the visual themes
> -------------------------------------------------------------------------------------
>
>                 Key: OFBIZ-4396
>                 URL: https://issues.apache.org/jira/browse/OFBIZ-4396
>             Project: OFBiz
>          Issue Type: Bug
>          Components: specialpurpose/projectmgr
>    Affects Versions: Release 10.04
>         Environment: RHEL 5.5
> JDK 1.6
> MySQL 5
>            Reporter: Tolulope Aganga-Williams
>            Priority: Minor
>              Labels: jsgantt, projectmgr
>
> The Gannt chart displays incorrectly in every browser and using any visual theme. The chart does not align the task on the left to the progress bar on the right. The problem is bad to severe depending on which visual theme you have enabled. I have even updated to the latest JSGantt some improvement but does not fix it.

--
This message is automatically generated by JIRA.
If you think it was sent incorrectly, please contact your JIRA administrators: https://issues.apache.org/jira/secure/ContactAdministrators!default.jspa
For more information on JIRA, see: http://www.atlassian.com/software/jira

       
Reply | Threaded
Open this post in threaded view
|

[jira] [Commented] (OFBIZ-4396) Project Manager Gantt chart does not display correctly using any of the visual themes

Nicolas Malin (Jira)
In reply to this post by Nicolas Malin (Jira)

    [ https://issues.apache.org/jira/browse/OFBIZ-4396?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=13119468#comment-13119468 ]

Tolulope Aganga-Williams commented on OFBIZ-4396:
-------------------------------------------------

Ok, your link didn't have any context when you posted it. I'll look into it.
               

> Project Manager Gantt chart does not display correctly using any of the visual themes
> -------------------------------------------------------------------------------------
>
>                 Key: OFBIZ-4396
>                 URL: https://issues.apache.org/jira/browse/OFBIZ-4396
>             Project: OFBiz
>          Issue Type: Bug
>          Components: specialpurpose/projectmgr
>    Affects Versions: Release 10.04
>         Environment: RHEL 5.5
> JDK 1.6
> MySQL 5
>            Reporter: Tolulope Aganga-Williams
>            Priority: Minor
>              Labels: jsgantt, projectmgr
>
> The Gannt chart displays incorrectly in every browser and using any visual theme. The chart does not align the task on the left to the progress bar on the right. The problem is bad to severe depending on which visual theme you have enabled. I have even updated to the latest JSGantt some improvement but does not fix it.

--
This message is automatically generated by JIRA.
If you think it was sent incorrectly, please contact your JIRA administrators: https://issues.apache.org/jira/secure/ContactAdministrators!default.jspa
For more information on JIRA, see: http://www.atlassian.com/software/jira

       
Reply | Threaded
Open this post in threaded view
|

[jira] [Commented] (OFBIZ-4396) Project Manager Gantt chart does not display correctly using any of the visual themes

Nicolas Malin (Jira)
In reply to this post by Nicolas Malin (Jira)

    [ https://issues.apache.org/jira/browse/OFBIZ-4396?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=13119571#comment-13119571 ]

Erwan de FERRIERES commented on OFBIZ-4396:
-------------------------------------------

have you tried on the trunk ?
Is it only related to 10.04 ?
               

> Project Manager Gantt chart does not display correctly using any of the visual themes
> -------------------------------------------------------------------------------------
>
>                 Key: OFBIZ-4396
>                 URL: https://issues.apache.org/jira/browse/OFBIZ-4396
>             Project: OFBiz
>          Issue Type: Bug
>          Components: specialpurpose/projectmgr
>    Affects Versions: Release 10.04
>         Environment: RHEL 5.5
> JDK 1.6
> MySQL 5
>            Reporter: Tolulope Aganga-Williams
>            Priority: Minor
>              Labels: jsgantt, projectmgr
>
> The Gannt chart displays incorrectly in every browser and using any visual theme. The chart does not align the task on the left to the progress bar on the right. The problem is bad to severe depending on which visual theme you have enabled. I have even updated to the latest JSGantt some improvement but does not fix it.

--
This message is automatically generated by JIRA.
If you think it was sent incorrectly, please contact your JIRA administrators: https://issues.apache.org/jira/secure/ContactAdministrators!default.jspa
For more information on JIRA, see: http://www.atlassian.com/software/jira

       
Reply | Threaded
Open this post in threaded view
|

[jira] [Commented] (OFBIZ-4396) Project Manager Gantt chart does not display correctly using any of the visual themes

Nicolas Malin (Jira)
In reply to this post by Nicolas Malin (Jira)

    [ https://issues.apache.org/jira/browse/OFBIZ-4396?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=13119608#comment-13119608 ]

Tolulope Aganga-Williams commented on OFBIZ-4396:
-------------------------------------------------

Erwan, it is in the trunk also, you can see the issue in the Demo environment if you add a bunch of phases and tasks.

Thanks!
               

> Project Manager Gantt chart does not display correctly using any of the visual themes
> -------------------------------------------------------------------------------------
>
>                 Key: OFBIZ-4396
>                 URL: https://issues.apache.org/jira/browse/OFBIZ-4396
>             Project: OFBiz
>          Issue Type: Bug
>          Components: specialpurpose/projectmgr
>    Affects Versions: Release 10.04
>         Environment: RHEL 5.5
> JDK 1.6
> MySQL 5
>            Reporter: Tolulope Aganga-Williams
>            Priority: Minor
>              Labels: jsgantt, projectmgr
>
> The Gannt chart displays incorrectly in every browser and using any visual theme. The chart does not align the task on the left to the progress bar on the right. The problem is bad to severe depending on which visual theme you have enabled. I have even updated to the latest JSGantt some improvement but does not fix it.

--
This message is automatically generated by JIRA.
If you think it was sent incorrectly, please contact your JIRA administrators: https://issues.apache.org/jira/secure/ContactAdministrators!default.jspa
For more information on JIRA, see: http://www.atlassian.com/software/jira

       
Reply | Threaded
Open this post in threaded view
|

[jira] [Issue Comment Edited] (OFBIZ-4396) Project Manager Gantt chart does not display correctly using any of the visual themes

Nicolas Malin (Jira)
In reply to this post by Nicolas Malin (Jira)

    [ https://issues.apache.org/jira/browse/OFBIZ-4396?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=13119608#comment-13119608 ]

Tolulope Aganga-Williams edited comment on OFBIZ-4396 at 10/3/11 9:05 PM:
--------------------------------------------------------------------------

Erwan, it is in the trunk also, you can see the issue in the Demo environment if you add a bunch of phases and tasks.

Just load the demo-trunk ofbiz at the following url

https://demo-trunk.ofbiz.apache.org:8443/projectmgr/control/ganttChart?projectId=9000

Thanks!
               
      was (Author: [hidden email]):
    Erwan, it is in the trunk also, you can see the issue in the Demo environment if you add a bunch of phases and tasks.

Thanks!
                 

> Project Manager Gantt chart does not display correctly using any of the visual themes
> -------------------------------------------------------------------------------------
>
>                 Key: OFBIZ-4396
>                 URL: https://issues.apache.org/jira/browse/OFBIZ-4396
>             Project: OFBiz
>          Issue Type: Bug
>          Components: specialpurpose/projectmgr
>    Affects Versions: Release 10.04
>         Environment: RHEL 5.5
> JDK 1.6
> MySQL 5
>            Reporter: Tolulope Aganga-Williams
>            Priority: Minor
>              Labels: jsgantt, projectmgr
>
> The Gannt chart displays incorrectly in every browser and using any visual theme. The chart does not align the task on the left to the progress bar on the right. The problem is bad to severe depending on which visual theme you have enabled. I have even updated to the latest JSGantt some improvement but does not fix it.

--
This message is automatically generated by JIRA.
If you think it was sent incorrectly, please contact your JIRA administrators: https://issues.apache.org/jira/secure/ContactAdministrators!default.jspa
For more information on JIRA, see: http://www.atlassian.com/software/jira

       
Reply | Threaded
Open this post in threaded view
|

[jira] [Commented] (OFBIZ-4396) Project Manager Gantt chart does not display correctly using any of the visual themes

Nicolas Malin (Jira)
In reply to this post by Nicolas Malin (Jira)

    [ https://issues.apache.org/jira/browse/OFBIZ-4396?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=13119619#comment-13119619 ]

Erwan de FERRIERES commented on OFBIZ-4396:
-------------------------------------------

if you remove totally the theme CSS, then the Gantt is well displayed. You should search this way to make it work, by understanding which properties are in conflict.
               

> Project Manager Gantt chart does not display correctly using any of the visual themes
> -------------------------------------------------------------------------------------
>
>                 Key: OFBIZ-4396
>                 URL: https://issues.apache.org/jira/browse/OFBIZ-4396
>             Project: OFBiz
>          Issue Type: Bug
>          Components: specialpurpose/projectmgr
>    Affects Versions: Release 10.04
>         Environment: RHEL 5.5
> JDK 1.6
> MySQL 5
>            Reporter: Tolulope Aganga-Williams
>            Priority: Minor
>              Labels: jsgantt, projectmgr
>
> The Gannt chart displays incorrectly in every browser and using any visual theme. The chart does not align the task on the left to the progress bar on the right. The problem is bad to severe depending on which visual theme you have enabled. I have even updated to the latest JSGantt some improvement but does not fix it.

--
This message is automatically generated by JIRA.
If you think it was sent incorrectly, please contact your JIRA administrators: https://issues.apache.org/jira/secure/ContactAdministrators!default.jspa
For more information on JIRA, see: http://www.atlassian.com/software/jira

       
Reply | Threaded
Open this post in threaded view
|

[jira] [Commented] (OFBIZ-4396) Project Manager Gantt chart does not display correctly using any of the visual themes

Nicolas Malin (Jira)
In reply to this post by Nicolas Malin (Jira)

    [ https://issues.apache.org/jira/browse/OFBIZ-4396?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=13119641#comment-13119641 ]

Tolu Williams commented on OFBIZ-4396:
--------------------------------------

I just started looking at the theme now, but being that there is no single
theme in the trunk that display this thing correctly shouldn't this be
classified as a bug? Whats a work around, i can't use ofbiz and disable the
theme for some pages. There are several places where this thing could be
broken. Would a quick fix be to just pop the gantt chart in a seperate
window that has no style?

Thanks.

On Mon, Oct 3, 2011 at 5:17 PM, Erwan de FERRIERES (Commented) (JIRA) <



--
Tolu Williams
Principal Consultant
www.cultureshockmedia.com
(240) 353-6742

               

> Project Manager Gantt chart does not display correctly using any of the visual themes
> -------------------------------------------------------------------------------------
>
>                 Key: OFBIZ-4396
>                 URL: https://issues.apache.org/jira/browse/OFBIZ-4396
>             Project: OFBiz
>          Issue Type: Bug
>          Components: specialpurpose/projectmgr
>    Affects Versions: Release 10.04
>         Environment: RHEL 5.5
> JDK 1.6
> MySQL 5
>            Reporter: Tolulope Aganga-Williams
>            Priority: Minor
>              Labels: jsgantt, projectmgr
>
> The Gannt chart displays incorrectly in every browser and using any visual theme. The chart does not align the task on the left to the progress bar on the right. The problem is bad to severe depending on which visual theme you have enabled. I have even updated to the latest JSGantt some improvement but does not fix it.

--
This message is automatically generated by JIRA.
If you think it was sent incorrectly, please contact your JIRA administrators: https://issues.apache.org/jira/secure/ContactAdministrators!default.jspa
For more information on JIRA, see: http://www.atlassian.com/software/jira

       
Reply | Threaded
Open this post in threaded view
|

[jira] [Commented] (OFBIZ-4396) Project Manager Gantt chart does not display correctly using any of the visual themes

Nicolas Malin (Jira)
In reply to this post by Nicolas Malin (Jira)

    [ https://issues.apache.org/jira/browse/OFBIZ-4396?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=13119653#comment-13119653 ]

Erwan de FERRIERES commented on OFBIZ-4396:
-------------------------------------------

Sure this is a bug, and your contribution is very welcome to correct and improve the project !
               

> Project Manager Gantt chart does not display correctly using any of the visual themes
> -------------------------------------------------------------------------------------
>
>                 Key: OFBIZ-4396
>                 URL: https://issues.apache.org/jira/browse/OFBIZ-4396
>             Project: OFBiz
>          Issue Type: Bug
>          Components: specialpurpose/projectmgr
>    Affects Versions: Release 10.04
>         Environment: RHEL 5.5
> JDK 1.6
> MySQL 5
>            Reporter: Tolulope Aganga-Williams
>            Priority: Minor
>              Labels: jsgantt, projectmgr
>
> The Gannt chart displays incorrectly in every browser and using any visual theme. The chart does not align the task on the left to the progress bar on the right. The problem is bad to severe depending on which visual theme you have enabled. I have even updated to the latest JSGantt some improvement but does not fix it.

--
This message is automatically generated by JIRA.
If you think it was sent incorrectly, please contact your JIRA administrators: https://issues.apache.org/jira/secure/ContactAdministrators!default.jspa
For more information on JIRA, see: http://www.atlassian.com/software/jira

       
Reply | Threaded
Open this post in threaded view
|

[jira] [Commented] (OFBIZ-4396) Project Manager Gantt chart does not display correctly using any of the visual themes

Nicolas Malin (Jira)
In reply to this post by Nicolas Malin (Jira)

    [ https://issues.apache.org/jira/browse/OFBIZ-4396?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=13119982#comment-13119982 ]

Erwan de FERRIERES commented on OFBIZ-4396:
-------------------------------------------

BTW, gantt chart is well displayed with firefox and tomawhak theme
               

> Project Manager Gantt chart does not display correctly using any of the visual themes
> -------------------------------------------------------------------------------------
>
>                 Key: OFBIZ-4396
>                 URL: https://issues.apache.org/jira/browse/OFBIZ-4396
>             Project: OFBiz
>          Issue Type: Bug
>          Components: specialpurpose/projectmgr
>    Affects Versions: Release 10.04
>         Environment: RHEL 5.5
> JDK 1.6
> MySQL 5
>            Reporter: Tolulope Aganga-Williams
>            Priority: Minor
>              Labels: jsgantt, projectmgr
>
> The Gannt chart displays incorrectly in every browser and using any visual theme. The chart does not align the task on the left to the progress bar on the right. The problem is bad to severe depending on which visual theme you have enabled. I have even updated to the latest JSGantt some improvement but does not fix it.

--
This message is automatically generated by JIRA.
If you think it was sent incorrectly, please contact your JIRA administrators: https://issues.apache.org/jira/secure/ContactAdministrators!default.jspa
For more information on JIRA, see: http://www.atlassian.com/software/jira

       
Reply | Threaded
Open this post in threaded view
|

[jira] [Commented] (OFBIZ-4396) Project Manager Gantt chart does not display correctly using any of the visual themes

Nicolas Malin (Jira)
In reply to this post by Nicolas Malin (Jira)

    [ https://issues.apache.org/jira/browse/OFBIZ-4396?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=13120179#comment-13120179 ]

Tolulope Aganga-Williams commented on OFBIZ-4396:
-------------------------------------------------

Thanks Erwan, its actually displayed FLAWLESSLY in Google chrome with the Tomahawk theme.

Its an ugly ass theme though but i will take what i can get. I'll try to find time and troubleshoot the issue in my favorite theme.

Thanks!
               

> Project Manager Gantt chart does not display correctly using any of the visual themes
> -------------------------------------------------------------------------------------
>
>                 Key: OFBIZ-4396
>                 URL: https://issues.apache.org/jira/browse/OFBIZ-4396
>             Project: OFBiz
>          Issue Type: Bug
>          Components: specialpurpose/projectmgr
>    Affects Versions: Release 10.04
>         Environment: RHEL 5.5
> JDK 1.6
> MySQL 5
>            Reporter: Tolulope Aganga-Williams
>            Priority: Minor
>              Labels: jsgantt, projectmgr
>
> The Gannt chart displays incorrectly in every browser and using any visual theme. The chart does not align the task on the left to the progress bar on the right. The problem is bad to severe depending on which visual theme you have enabled. I have even updated to the latest JSGantt some improvement but does not fix it.

--
This message is automatically generated by JIRA.
If you think it was sent incorrectly, please contact your JIRA administrators: https://issues.apache.org/jira/secure/ContactAdministrators!default.jspa
For more information on JIRA, see: http://www.atlassian.com/software/jira

       
Reply | Threaded
Open this post in threaded view
|

[jira] [Commented] (OFBIZ-4396) Project Manager Gantt chart does not display correctly using any of the visual themes

Nicolas Malin (Jira)
In reply to this post by Nicolas Malin (Jira)

    [ https://issues.apache.org/jira/browse/OFBIZ-4396?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=13120254#comment-13120254 ]

Jacques Le Roux commented on OFBIZ-4396:
----------------------------------------

Why don't you like Tomahawk? It's currently our default theme and most advanced, though it does not handle RTL languages
               

> Project Manager Gantt chart does not display correctly using any of the visual themes
> -------------------------------------------------------------------------------------
>
>                 Key: OFBIZ-4396
>                 URL: https://issues.apache.org/jira/browse/OFBIZ-4396
>             Project: OFBiz
>          Issue Type: Bug
>          Components: specialpurpose/projectmgr
>    Affects Versions: Release 10.04
>         Environment: RHEL 5.5
> JDK 1.6
> MySQL 5
>            Reporter: Tolulope Aganga-Williams
>            Priority: Minor
>              Labels: jsgantt, projectmgr
>
> The Gannt chart displays incorrectly in every browser and using any visual theme. The chart does not align the task on the left to the progress bar on the right. The problem is bad to severe depending on which visual theme you have enabled. I have even updated to the latest JSGantt some improvement but does not fix it.

--
This message is automatically generated by JIRA.
If you think it was sent incorrectly, please contact your JIRA administrators: https://issues.apache.org/jira/secure/ContactAdministrators!default.jspa
For more information on JIRA, see: http://www.atlassian.com/software/jira

       
Reply | Threaded
Open this post in threaded view
|

[jira] [Commented] (OFBIZ-4396) Project Manager Gantt chart does not display correctly using any of the visual themes

Nicolas Malin (Jira)
In reply to this post by Nicolas Malin (Jira)

    [ https://issues.apache.org/jira/browse/OFBIZ-4396?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=13120261#comment-13120261 ]

Tolulope Aganga-Williams commented on OFBIZ-4396:
-------------------------------------------------

Well, the layout is fine, the colors are pretty jarring to me. I supposed i could tweak the css to my liking right?
               

> Project Manager Gantt chart does not display correctly using any of the visual themes
> -------------------------------------------------------------------------------------
>
>                 Key: OFBIZ-4396
>                 URL: https://issues.apache.org/jira/browse/OFBIZ-4396
>             Project: OFBiz
>          Issue Type: Bug
>          Components: specialpurpose/projectmgr
>    Affects Versions: Release 10.04
>         Environment: RHEL 5.5
> JDK 1.6
> MySQL 5
>            Reporter: Tolulope Aganga-Williams
>            Priority: Minor
>              Labels: jsgantt, projectmgr
>
> The Gannt chart displays incorrectly in every browser and using any visual theme. The chart does not align the task on the left to the progress bar on the right. The problem is bad to severe depending on which visual theme you have enabled. I have even updated to the latest JSGantt some improvement but does not fix it.

--
This message is automatically generated by JIRA.
If you think it was sent incorrectly, please contact your JIRA administrators: https://issues.apache.org/jira/secure/ContactAdministrators!default.jspa
For more information on JIRA, see: http://www.atlassian.com/software/jira

       
Reply | Threaded
Open this post in threaded view
|

[jira] [Commented] (OFBIZ-4396) Project Manager Gantt chart does not display correctly using any of the visual themes

Nicolas Malin (Jira)
In reply to this post by Nicolas Malin (Jira)

    [ https://issues.apache.org/jira/browse/OFBIZ-4396?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=13120282#comment-13120282 ]

Jacques Le Roux commented on OFBIZ-4396:
----------------------------------------

yes sure, it's up to you. You could even contribute the result of your work as a new theme (based on Tomahawk). This is actually how it works...
               

> Project Manager Gantt chart does not display correctly using any of the visual themes
> -------------------------------------------------------------------------------------
>
>                 Key: OFBIZ-4396
>                 URL: https://issues.apache.org/jira/browse/OFBIZ-4396
>             Project: OFBiz
>          Issue Type: Bug
>          Components: specialpurpose/projectmgr
>    Affects Versions: Release 10.04
>         Environment: RHEL 5.5
> JDK 1.6
> MySQL 5
>            Reporter: Tolulope Aganga-Williams
>            Priority: Minor
>              Labels: jsgantt, projectmgr
>
> The Gannt chart displays incorrectly in every browser and using any visual theme. The chart does not align the task on the left to the progress bar on the right. The problem is bad to severe depending on which visual theme you have enabled. I have even updated to the latest JSGantt some improvement but does not fix it.

--
This message is automatically generated by JIRA.
If you think it was sent incorrectly, please contact your JIRA administrators: https://issues.apache.org/jira/secure/ContactAdministrators!default.jspa
For more information on JIRA, see: http://www.atlassian.com/software/jira

       
Reply | Threaded
Open this post in threaded view
|

[jira] [Commented] (OFBIZ-4396) Project Manager Gantt chart does not display correctly using any of the visual themes

Nicolas Malin (Jira)
In reply to this post by Nicolas Malin (Jira)

    [ https://issues.apache.org/jira/browse/OFBIZ-4396?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=13120297#comment-13120297 ]

Tolulope Aganga-Williams commented on OFBIZ-4396:
-------------------------------------------------

Of course! but you only want to contribute useful, working code back. Also i don't believe i have commit privileges.
               

> Project Manager Gantt chart does not display correctly using any of the visual themes
> -------------------------------------------------------------------------------------
>
>                 Key: OFBIZ-4396
>                 URL: https://issues.apache.org/jira/browse/OFBIZ-4396
>             Project: OFBiz
>          Issue Type: Bug
>          Components: specialpurpose/projectmgr
>    Affects Versions: Release 10.04
>         Environment: RHEL 5.5
> JDK 1.6
> MySQL 5
>            Reporter: Tolulope Aganga-Williams
>            Priority: Minor
>              Labels: jsgantt, projectmgr
>
> The Gannt chart displays incorrectly in every browser and using any visual theme. The chart does not align the task on the left to the progress bar on the right. The problem is bad to severe depending on which visual theme you have enabled. I have even updated to the latest JSGantt some improvement but does not fix it.

--
This message is automatically generated by JIRA.
If you think it was sent incorrectly, please contact your JIRA administrators: https://issues.apache.org/jira/secure/ContactAdministrators!default.jspa
For more information on JIRA, see: http://www.atlassian.com/software/jira

       
Reply | Threaded
Open this post in threaded view
|

[jira] [Commented] (OFBIZ-4396) Project Manager Gantt chart does not display correctly using any of the visual themes

Nicolas Malin (Jira)
In reply to this post by Nicolas Malin (Jira)

    [ https://issues.apache.org/jira/browse/OFBIZ-4396?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=13120310#comment-13120310 ]

BJ Freeman commented on OFBIZ-4396:
-----------------------------------

Either change the Flat Grey or Create a New theme that has all the bells an whistles you want an Give you the support for the Gnatt  and submit a patch to this Jira
               

> Project Manager Gantt chart does not display correctly using any of the visual themes
> -------------------------------------------------------------------------------------
>
>                 Key: OFBIZ-4396
>                 URL: https://issues.apache.org/jira/browse/OFBIZ-4396
>             Project: OFBiz
>          Issue Type: Bug
>          Components: specialpurpose/projectmgr
>    Affects Versions: Release 10.04
>         Environment: RHEL 5.5
> JDK 1.6
> MySQL 5
>            Reporter: Tolulope Aganga-Williams
>            Priority: Minor
>              Labels: jsgantt, projectmgr
>
> The Gannt chart displays incorrectly in every browser and using any visual theme. The chart does not align the task on the left to the progress bar on the right. The problem is bad to severe depending on which visual theme you have enabled. I have even updated to the latest JSGantt some improvement but does not fix it.

--
This message is automatically generated by JIRA.
If you think it was sent incorrectly, please contact your JIRA administrators: https://issues.apache.org/jira/secure/ContactAdministrators!default.jspa
For more information on JIRA, see: http://www.atlassian.com/software/jira

       
Reply | Threaded
Open this post in threaded view
|

[jira] [Commented] (OFBIZ-4396) Project Manager Gantt chart does not display correctly using any of the visual themes

Nicolas Malin (Jira)
In reply to this post by Nicolas Malin (Jira)

    [ https://issues.apache.org/jira/browse/OFBIZ-4396?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=13120325#comment-13120325 ]

Jacques Le Roux commented on OFBIZ-4396:
----------------------------------------

You don't need commit privileges. Simply submit a patch as BJ suggested. You may follow https://cwiki.apache.org/confluence/display/OFBADMIN/OFBiz+Contributors+Best+Practices to help you
               

> Project Manager Gantt chart does not display correctly using any of the visual themes
> -------------------------------------------------------------------------------------
>
>                 Key: OFBIZ-4396
>                 URL: https://issues.apache.org/jira/browse/OFBIZ-4396
>             Project: OFBiz
>          Issue Type: Bug
>          Components: specialpurpose/projectmgr
>    Affects Versions: Release 10.04
>         Environment: RHEL 5.5
> JDK 1.6
> MySQL 5
>            Reporter: Tolulope Aganga-Williams
>            Priority: Minor
>              Labels: jsgantt, projectmgr
>
> The Gannt chart displays incorrectly in every browser and using any visual theme. The chart does not align the task on the left to the progress bar on the right. The problem is bad to severe depending on which visual theme you have enabled. I have even updated to the latest JSGantt some improvement but does not fix it.

--
This message is automatically generated by JIRA.
If you think it was sent incorrectly, please contact your JIRA administrators: https://issues.apache.org/jira/secure/ContactAdministrators!default.jspa
For more information on JIRA, see: http://www.atlassian.com/software/jira

       
Reply | Threaded
Open this post in threaded view
|

[jira] [Commented] (OFBIZ-4396) Project Manager Gantt chart does not display correctly using any of the visual themes

Nicolas Malin (Jira)
In reply to this post by Nicolas Malin (Jira)

    [ https://issues.apache.org/jira/browse/OFBIZ-4396?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=13120349#comment-13120349 ]

Tolulope Aganga-Williams commented on OFBIZ-4396:
-------------------------------------------------

Thanks for the pointers!
               

> Project Manager Gantt chart does not display correctly using any of the visual themes
> -------------------------------------------------------------------------------------
>
>                 Key: OFBIZ-4396
>                 URL: https://issues.apache.org/jira/browse/OFBIZ-4396
>             Project: OFBiz
>          Issue Type: Bug
>          Components: specialpurpose/projectmgr
>    Affects Versions: Release 10.04
>         Environment: RHEL 5.5
> JDK 1.6
> MySQL 5
>            Reporter: Tolulope Aganga-Williams
>            Priority: Minor
>              Labels: jsgantt, projectmgr
>
> The Gannt chart displays incorrectly in every browser and using any visual theme. The chart does not align the task on the left to the progress bar on the right. The problem is bad to severe depending on which visual theme you have enabled. I have even updated to the latest JSGantt some improvement but does not fix it.

--
This message is automatically generated by JIRA.
If you think it was sent incorrectly, please contact your JIRA administrators: https://issues.apache.org/jira/secure/ContactAdministrators!default.jspa
For more information on JIRA, see: http://www.atlassian.com/software/jira

       
Reply | Threaded
Open this post in threaded view
|

[jira] [Commented] (OFBIZ-4396) Project Manager Gantt chart does not display correctly using any of the visual themes

Nicolas Malin (Jira)
In reply to this post by Nicolas Malin (Jira)

    [ https://issues.apache.org/jira/browse/OFBIZ-4396?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=13120374#comment-13120374 ]

BJ Freeman commented on OFBIZ-4396:
-----------------------------------

https://issues.apache.org/jira/browse/OFBIZ-3490
may be helpful
               

> Project Manager Gantt chart does not display correctly using any of the visual themes
> -------------------------------------------------------------------------------------
>
>                 Key: OFBIZ-4396
>                 URL: https://issues.apache.org/jira/browse/OFBIZ-4396
>             Project: OFBiz
>          Issue Type: Bug
>          Components: specialpurpose/projectmgr
>    Affects Versions: Release 10.04
>         Environment: RHEL 5.5
> JDK 1.6
> MySQL 5
>            Reporter: Tolulope Aganga-Williams
>            Priority: Minor
>              Labels: jsgantt, projectmgr
>
> The Gannt chart displays incorrectly in every browser and using any visual theme. The chart does not align the task on the left to the progress bar on the right. The problem is bad to severe depending on which visual theme you have enabled. I have even updated to the latest JSGantt some improvement but does not fix it.

--
This message is automatically generated by JIRA.
If you think it was sent incorrectly, please contact your JIRA administrators: https://issues.apache.org/jira/secure/ContactAdministrators!default.jspa
For more information on JIRA, see: http://www.atlassian.com/software/jira

       
12